Quantity takeoff template

A quantity takeoff is a measured list of the work on a job. Each line has a description, a unit and a quantity. You add your own rates to turn it into an estimate. It is not a bid and not a contract. General contractors use it to price the same scope, then roll it into a schedule of values.

A quantity takeoff you can read with JavaScript off

Quantities are sample measures only. Rates are blank. Type your own figures in the builder below. The result is an estimate, never a bid.

Sample measured lines for a small residential job. No rates are supplied.
DivisionDescriptionUnitQuantityRate
01: Job setup and general conditionsMobilize and temporary facilitiesls1-
03: Footings, slabs and other cast workFooting concretecu yd10-
03: Footings, slabs and other cast workSlab on gradesq ft480-
04: Brick, block and stoneFace brick veneersq ft520-
06: Framing and other woodworkFloor joistslf260-
09: Interior finishesGypsum board on wallssq ft650-
09: Interior finishesVinyl floor finishsq ft300-
32: Paving and outdoor workCrushed stone at gradeton8-

This table is in the page HTML. The builder enhances it. It does not replace it.

The builder opens in your browser. The example table above stays readable.

How this takeoff is grouped

These groups follow a specification and procurement layout. They are not a UK work-section bill, and they are not a functional building-system breakdown.

GroupWhat belongs here
01: Job setup and general conditionsMobilize, trailers, temp power and other job-wide setup.
02: Site clearing and earthworkClearing, stripping and earth that serves the pad.
03: Footings, slabs and other cast workFootings, walls, slabs and other cast-in-place work.
04: Brick, block and stoneBrick, block and stone. Coverage rates are yours.
05: Steel and miscellaneous metalStructural steel and miscellaneous metal.
06: Framing and other woodworkFraming, joists and other woodwork in linear feet.
07: Weather barrier and roofingWeather barrier, insulation and roofing.
08: Doors, windows and other openingsDoors, windows and other openings.
09: Interior finishesGypsum board, flooring and other interior finishes.
22: PlumbingPlumbing rough and finish.
23: Heating and airHeating, air and related equipment.
26: Power and lightingPower, lighting and low voltage you measure.
31: Earthwork beyond the buildingEarthwork beyond the building line.
32: Paving and outdoor workPaving, walks and other outdoor work.

Licensing for official specification titles is an open legal check. These labels are ours.

How do I prepare a quantity takeoff?

Read the drawing once for the structure. Then walk each division and write a line for every measured item.

Put the unit next to the quantity before you think about money. Rates come last, and they are yours.

Quantity takeoff is not a schedule of values

A takeoff measures work. A schedule of values is how a general contractor bills that work across the job.

You can start from this list. You still have to group lines the way your pay app is written.

Why MasterFormat-style grouping is not UniFormat

A specification layout groups by work result, material and trade. That suits buyout and bid packages.

A functional layout groups by building system. That suits an early elemental estimate. This tool does not mix them.

Need a client-facing bid letter instead?

A takeoff is for your desk. A bid letter names the parties, the price and what is out of scope.

How a plan becomes a takeoff

This template starts after you already have quantities. How a sheet is measured, and who checks it, is a separate page.

Need a lumberyard list instead of a takeoff?

A takeoff prices labor and divisions so two firms can be compared. A material list only names products and counts.

Where the rates on this takeoff come from

This template starts with blank rates. Type figures you can defend. We do not ship a US rate library to load.

About this quantity takeoff template

Use sq ft, cu yd, ft, ea, ls or ton, or switch the tool to metric. Pick one unit per line.

Checking a floor plan at a desk with a scale rule
Working through a drawing with a scale and a calculator

Need the buying list instead?

Open the material takeoff and type wall and floor sizes. Coverage rates on that page are yours.